Most min-max levels in a mine’s warehouse were set once, from historical usage, and then left alone. The fleet changes, the strategy changes, the supplier changes, and the levels don’t. The result is familiar: shelves full of parts nobody uses, and a planned stop that waits two days for a filter kit.
There is a better starting point: the maintenance strategy itself.
Start from what the strategy will use
A maintenance strategy already says what will be done, to which machines, and how often. That makes it a forecast of parts demand:
- Planned tasks: every PM service and inspection has a bill of materials. Multiply by the number of units and the interval, and you have a usage rate in parts per week.
- Component change-outs: the change-out forecast says which engines, transmissions and wheel motors will come out, and when.
- Breakdown parts: some demand is unplanned. For these, history is still the best guide, but strip out the failures the new strategy is designed to prevent.
The minimum is the reorder point
The minimum is the stock level that triggers an order. It needs to cover what you will use while the order is on its way:
Minimum = (usage per week × lead time in weeks) + safety stock
Two things matter here.
Use real lead times. The lead time in the item master is often the catalogue figure. The lead time that matters is from raising the order to the part sitting on your shelf at site, including freight to a remote mine. Purchase history tells you what it really is.
Size safety stock by consequence. A part whose absence parks a haul truck deserves more safety stock than one that can wait a day. Rank parts by the cost of a stock-out, not just by how often they move.
The maximum is the minimum plus a sensible order
Maximum = minimum + order quantity
The order quantity balances ordering cost, price breaks, shelf life and warehouse space. For most consumables it is a few weeks of usage. For expensive, slow-moving items it may be one.
Critical spares are a separate decision
Some parts rarely move but are essential when they do: a final drive, a slew ring, a large hydraulic pump with a long lead time. Usage-based min-max would hold none of them. These are critical spares, held on purpose, and the decision to hold them belongs in the site workshop, with maintenance and supply in the same room.
Review the levels when the strategy changes
Min-max levels are only right while the inputs are right. Review them when:
- the strategy changes intervals or adds tasks;
- the fleet grows, shrinks or changes model;
- a supplier’s lead time changes;
- a planned job is delayed by a stock-out.
Where this fits
Setting parts from the strategy is stop 06 of our reliability program. It comes after the strategy has been agreed at the site workshop, because that is when the demand is finally known. Read more about spares and min-max.